Transport of key equipment to Karachi project completed
2019.12.23The transportation of high-voltage modules for the No 3 unit for Pakistan's nuclear K2 and K3 projects was recently completed, when the truck carrying the units arrived at project site in Karachi, officials said.
-
Landmark moment as power switch turned on at key HPR 1000 reactor
2019.12.23It was a special moment as a 500 kilovolt combination switch for the No 2 nuclear reactor was powered on in the city of Karachi in Pakistan on Nov 29, officials said.
-
Cold functional test of China-built K2 reactor succeeds
2019.12.23The first overseas reactor of China's homegrown third-generation nuclear reactor technology -- the Hualong One or HPR 1000 -- was tested successfully in Pakistan on Dec 2, according to local officials.
-
CNNC's Zhangzhou nuclear plant goes into construction
2019.12.23The Zhangzhou Hualong One (HPR 1000) facility in East China's Fujian province began construction on Oct 16.
-
Installation of major equipment of first Huanglong One overseas reactor completed
2019.12.23Installation of all the major equipment of the K-2 unit project in Karachi, Pakistan, the first overseas unit using Hualong One (HPR 1000) nuclear technology, have been completed, after the successful installation of the rotor into the stator on Oct 8.
-
Main pipes of Pakistan's Hualong One complete weld bonding
2019.12.23The main steam piping nuclear island at the Hualong One (HPR 1000) project was successfully weld bonded on Aug 28 in Karachi of Pakistan, marking the completion of the weld bonding for Hualong One’s main steam piping and main water feed piping, officials said.