Hualong one pressurizers finish production
2019.08.18The pressurizers of Fuqing Unit 6, a Hualong one (HPR1000) demonstration project, passed inspection on Aug 14, signifying that research and production of all pressurizers for the four Hualong one units, both in China and abroad, have been completed.
-
Hualong One outer containment dome construction completes
2019.12.23The concrete pouring of the outer containment dome of unit 5 of the Fuqing nuclear power plant -- the demonstration project for the first Hualong One reactor -- was completed successfully in Fuqing, a city of East China's Fujian province on July 14, officials said.
-
Pump motor installed at Karachi 2
2019.08.26The first reactor coolant pump motor for Unit 2 of the Karachi nuclear power plant (known as Karachi 2), China’s self-developed third-generation HPR1000 (Hualong 1) demonstration project in Pakistan, was lifted into place on Aug 23.
-
CNNC completes main pipe welding at Fuqing Unit 6
2019.06.25The welding of the main pipe on Fuqing Unit 6, part of the HPR1000 (Hualong 1) reactor currently being built in China’s Fujian province, was completed on June 24, according to a CNNC announcement.
-
Karachi Unit 2 receives dome
2019.06.18The outer containment dome of Karachi Unit 2 was successfully installed on June 17.
-
Cold functional test of Karachi K2 reactor enters countdown
2019.12.23The nuclear circuit flushing of the China-built K2 reactor in the Karachi nuclear power plant in Pakistan began on June 22, according to local news reports.