Fuel loading completed at Shin Hanul 1

The loading of all 241 fuel assemblies into the core of unit 1 at the Shin Hanul nuclear power plant in South Korea has been completed, Korea Hydro & Nuclear Power (KHNP) announced. The unit - the first of two APR-1400 reactors at the site - is scheduled to enter commercial operation in mid-2022 following tests at various power levels to ensure that all systems operate safely as designed.

Shin-Hanul-units-1-and-2-(KHNP).jpg

Shin Hanul units 1 and 2 (Image: KHNP)

Ground breaking for the first two units at the Shin Hanul (formerly Shin Ulchin) site took place in May 2012. First concrete for unit 1 was poured two months later, with that for unit 2 following in June 2013. The 1350 MWe pressurised water reactors were originally expected to enter service in April 2017 and April 2018, respectively. Following delays, fuel loading in unit 1 had been scheduled for June 2019 but was delayed pending safety checks by the Nuclear Safety and Security Committee (NSSC) and some modifications. Commercial operation of unit 1 was then expected in July 2021, and unit 2 in May 2022, but there have been further delays.

On 9 July, the NSSC gave its conditional approval for the start-up of Shina Hanul 1. KHNP began loading the first of the fuel assemblies into the core of the reactor five days later.

KHNP announced on 13 October that, following the completion of fuel loading, it is now conducting reactor physics and systems testing under normal operating temperature and pressure conditions. In July, the company said these tests were expected to take about eight months to complete.

The APR-1400 is an evolutionary pressurised water reactor with its origins in the CE System 80+ model. Principally designed by Korea Engineering Company, it produces 1400 MWe and has a 60-year design life. It supersedes the standardised 995 MWe OPR-1000 design, of which South Korea built 12. The APR-1400 features improvements in operation, safety, maintenance and affordability based on accumulated experience as well as technological development.

In October 2017, European Utility Requirements - a technical advisory group for European utilities on nuclear power plants - approved the APR-1400 reactor design. The US Nuclear Regulatory Commission certified the APR-1400 in August 2019, finding the design fully meets US safety requirements.

The first two APR-1400 units - Shin Kori 3 and 4 - entered commercial operation in December 2016 and September 2019, respectively. Construction of two further APR-1400s as Shin Kori units 5 and 6 began in April 2017 and September 2018. These are scheduled to be commissioned in March 2023 and June 2024.

KHNP noted Shin Hanul unit 1 is the first power reactor in South Korea to achieve technological independence through localisation of core facilities such as the reactor coolant pump and the plant instrumentation and control system.

Four APR-1400s have also been built at Barakah in the United Arab Emirates. The first two of these units were connected to the grid in August 2020 and September 2021, respectively.

Researched and written by World Nuclear News


Contact Us

No.1 Nansanxiang, Sanlihe, Beijing 100822, P.R. China

Tel: 86-10-68512211

Fax: 86-10-68533989

Please leave a message...

Your E-mail Adress

Copyright © China National Nuclear Corporation. All Rights Reserved.

Presented by China Daily. 京ICP备06041231号-1