2023-03-10
World's first international standard in nuclear fusion released
China's first international standard in nuclear fusion was released on March 6.
-
2023-02-22
Inner dome installed at Changjiang 3
The inner dome for unit 3 of the Changjiang nuclear power plant was successfully hoisted into place on Feb 21, in South China's Hainan province.
-
2023-02-21
Outer dome installed at CNNC's Zhangzhou 1
The outer dome for unit 1 of the China National Nuclear Corporation's (CNNC) Zhangzhou nuclear power plant was successfully hoisted into place on Feb 17, in East China's Fujian province.
-
2023-02-16
CNNC develops isotope light sources
The China Institute of Atomic Energy (CIAE) of the China National Nuclear Corporation (CNNC) has independently developed the AIE (Aggregation Induced Emission) isotope light source.
-
2023-02-02
Two units of the first overseas project of HPR1000 officially delivered
Unit 3 of the Karachi Nuclear Power Plant (K-3) was inaugurated in Pakistan on Feb 2.
-
2023-01-11
CNNC reports growth in power generation in 2022
CNNC generated nearly 218.74 billion kilowatt-hours of electricity from commercial operation in 2022, an increase of 21.97 billion kilowatt-hours over the same period of the previous year, up by 11.17 percent.
-
2022-12-28
CNNC supports frontier science research with germanium isotopes
The China Nuclear Energy Industry Corporation (CNEIC) of the CNNC has achieved independent and mass production of germanium (Ge) isotopes, having delivered the isotopes to Tsinghua University in late August of this year.
-
2022-12-28
CNNC's first self-developed BNCT cancer treatment facility settles in Tai'an, Shandong
The China Institute of Atomic Energy (CIAE) of the CNNC and the Tai'an City Central Hospital in Shandong province signed a cooperation agreement on the construction of a Boron Neutron Capture Therapy (BNCT) based treatment center on Dec 22.
-
2022-12-08
China's first homegrown main steam isolation valves delivered
The first three sets of China's domestically developed main steam isolation valves passed through acceptance tests on Nov 30.
-
2022-12-01
Obstacles to all key technologies for development of China's BNCT cancer treatment facility removed